How to Change Distribution Cycle in SAP – KSV2

How to Change Distribution Cycle in SAP – KSV2

Distribution Cycle: A distribution cycle in SAP is used to reallocate primary costs (like rent, utilities, admin expenses) from one cost center (the sender) to one or more other cost centers (the receivers) based on a defined rule, such as percentage or portions.

Scenario: In this blog, we demonstrate how to modify a distribution cycle in SAP, using a simple example of changing the cost-sharing percentage from 75% to 100%.

Go to T code: KSV2.

Now enter the Distribution cycle name and start date (Make sure about controlling area), then press the Enter key.

How to Change Distribution Cycle in SAP - KSV2

Note: Fields that are greyed out cannot be changed or edited.

Click on the first segment (in our scenario, we are updating the sharing percentage).

How to Change Distribution Cycle in SAP - KSV2

Old value:

How to Change Distribution Cycle in SAP - KSV2

Updating with new value:

How to Change Distribution Cycle in SAP - KSV2

Click on save button.

Now customizing request prompt will come, select your request and click on continue.

Successfully changed the distribution cycle.

Similar Content you may like:

  • How to Configure and Execute Distribution Cycle (KSV1 & KSV5) in SAP: Click here
  • How to Change Distribution Cycle (KSV2) in SAP: Click here
  • How to Display Distribution Cycle (KSV3) in SAP: Click here
  • How to Delete Distribution Cycle (KSV4) in SAP: Click here

SAP FICO Configuration topics:

How to Change Distribution Cycle in SAP – KSV2


Discover more from sap96.com

Subscribe to get the latest posts sent to your email.

Comment Here

Discover more from sap96.com

Subscribe now to keep reading and get access to the full archive.

Continue reading