How to Change Cost center in SAP S4 HANA – OKENN

How to Change Cost center in SAP S4 HANA – OKENN.

Cost Center: It is an organizational unit within controlling area and it manages costs associated with a specific functional area, department, or activity for internal reporting purpose (As it only captures the costs). Cost element will help here to integrate the CO with FI module.

Go to T code: OKENN (This screen allows you to efficiently organize and structure your cost centers in a hierarchical format).

Popup will come, Give Controlling Area and click on continue button.

How to Change Cost center in SAP S4 HANA – OKENN

We are currently in the Cost Center Group view. To proceed, double-click on the desired Cost Center.

How to Change Cost center in SAP S4 HANA – OKENN

Now click on change icon.

How to Change Cost center in SAP S4 HANA – OKENN

In this blog, we are changing the field ‘person responsible’.

How to Change Cost center in SAP S4 HANA – OKENN

Click on save button.

Cost center changed successfully.

Other contents you may like in SAP:
  • How to Create Controlling Area in SAP: Click here
  • How to Create the Cost Center (OKENN) in SAP: Click here
  • How to Display the Cost Center (OKENN) in SAP: Click here
  • Creation of Primary Cost Element GL in S4 Hana: Click here
  • Creation of Secondary Cost Element GL in S4 Hana: Click here

SAP FICO Configuration topics:

How to Change Cost center in SAP S4 HANA – OKENN


Discover more from sap96.com

Subscribe to get the latest posts sent to your email.

Comment Here